Board of Estimate & Contract:
Whereas, on April 18, 2024, DONNA WILLIAMS filed a Notice of Claim seeking the sum of $805.23 against the City of Mount Vernon for property damage allegedly caused to the claimant’s 2021 BMW by a defective sewer cover that was not completely on March 7, 2024; and
Whereas, by letter dated August 8, 2024, the Corporation Counsel hereby recommends that the Board of Estimate & Contract approve the settlement of the aforesaid claim for $805.23; Now, Therefore, be it
Resolved, that the aforesaid claim of DONNA WILLIAMS, be settled for the sum of $805.23 and that said settlement be and the same hereby is approved; and be it further
Resolved, that said sum be paid out of Budget Code A1910.469 (Insurance - Claims), 2024 Budget.