RESOLVED, that an ordinance adopted by the City Council on July 10, 2024, and signed by the Acting Mayor on July 10, 2024, authorizing the adoption of the resolution for the New York State Department of Transportation BRIDGE NY Rehabilitation project (BIN 2225220) and authorizing the initiation of the Engineering and Design phase for the South Fulton Avenue and East Third Street Bridge (Overpass) Rehabilitation project (with a total cost of $1,000,000 - (NYS share is $950,000 and the City's cash match is $50,000, which represents 5% of the total project cost - appropriation of $50,000 from the Engineering Office Budget Line A1440.405 to serve as the City's cash match for the Engineering and Design phase of the project), be and the same is hereby approved.
City Council:
AN ORDINANCE ADOPTING THE RESOLUTION
PROJECT (BIN 2225220) AND AUTHORIZING THE
ENGINEERING AND DESIGN PHASE FOR THE
SOUTH FULTON AVENUE AND EAST THIRD STREET
BRIDGE (OVERPASS) REHABILITATION PROJECT
Whereas, by letter dated July 9, 2024, the Commissioner of the Department of Public Works has requested legislation authorizing the adoption of the resolution for the New York State Department of Transportation BRIDGE NY Rehabilitation project (BIN 2225220) and authorizing the initiation of the Engineering and Design phase for the South Fulton Avenue and East Third Street Bridge (Overpass) Rehabilitation project, with a total cost of $1,000,000; and
Whereas, the total grant amount for the bridge rehabilitation project is $4,999,710, to be executed in two phases: Engineering & Design and Reconstruction; and
Whereas, this ordinance pertains specifically to the Engineering and Design phase, with a total cost of $1,000,000; and
Whereas, the cost share for the Engineering and Design phase is broken down as follows: NYS share is $950,000 and the City's cash match is $50,000, which represents 5% of the total project cost; and
Whereas, the Ci...