Board of Estimate & Contract:
A RESOLUTION AUTHORIZING THE
SETTLEMENT OF THE CLAIM OF
DIANE ATKINS
WHEREAS, on July 21, 2025, Diane Atkins submitted a Notice of Claim against the City of Mount Vernon seeking compensation for $441.36 for property damage; and
WHEREAS, the claimant asserts that on June 30, 2025, her vehicle’s tire and rim were damaged when a large, jagged pothole caused the tire to blow out and the rim to sustain damage; and
WHEREAS, by letter dated August 13, 2025, the Corporation Counsel recommended that the Board of Estimate & Contract approve the settlement of this claim of $441.36;
NOW, THEREFORE, BE IT RESOLVED, that the claim of Diane Atkins be settled for $441.36, and that said settlement is hereby approved; and be it further
RESOLVED, that payment of this sum shall be made from Budget Code A1910.469 (Insurance - Claims) in the 2025 Budget.