Board of Estimate & Contract:
RESOLVED, that an ordinance adopted by the City Council on August 13, 2025, and signed by the Mayor on August 14, 2025, authorizing the Mayor to Enter into an Emergency Contractual Agreement with Zonzini Pipeline Inc. for Sewer Rehabilitation Work at Macquesten and West Devonia Avenue and 115 Dell Avenue - (the total cost of $9,103.00 for this sewer rehabilitation project of for the shall be charged to Budget Line A8120.405); be, and the same is hereby approved.
City Council:
AN ORDINANCE AUTHORIZING THE MAYOR
TO ENTER INTO AN EMERGENCY CONTRACTUAL
AGREEMENT WITH ZONZINI PIPELINE INC. FOR
SEWER REHABILITATION WORK AT MACQUESTEN
AND WEST DEVONIA AVENUE AND 115 DELL AVENUE
Whereas, in correspondence dated June 16, 2025, the Commissioner of the Department of Public Works formally requested authorization for the Mayor to enter into an emergency contractual agreement with Zonzini Pipeline Inc. for the removal and replacement of concrete slabs above sanitary and storm sewer mains at Macquesten and West Devonia Avenue, and 115 Dell Avenue; and
Whereas, the Department of Public Works has identified hazardous conditions resulting from the settling of concrete slabs above critical city sanitary and storm sewer mains located at Macquesten and West Devonia Avenue, and 115 Dell Avenue; and
Whereas, the deterioration and settling of these concrete slabs pose an imminent danger to vehicles, pedestrians, and public safety, and risk further damage to essential infrastructure; and
Whereas, emergency action is required to remove and replace the compromised concrete roadways to prevent injury, mitigate potential damage, and ensure the uninterrupted operation of public services; and
Whereas, in accordance with Section 6(B) of the City of Mount Vernon's Procurement Policy, emergency purchases are permitted where delay may threaten the life, health, safety, or welfare of the residents or the City, and therefore, th...