File #: TMP -1099    Version: 1
Type: Ordinance Status: Adopted
File created: 12/17/2024 In control: City Council
On agenda: 12/23/2024 Final action: 12/23/2024
Title: Department of Public Works: An Ordinance Authorizing the Mayor to Amend the Agreement with National Water Main Cleaning Company to Extend the Contract End Date for Outfall 24 Sewer System Cleaning and Inspection Project 122022-1
Attachments: 1. Contract Amendment Request Outfall 24 Sewer System cleaning and Inspection Project 1220221-122024 Revision.pdf
Board of Estimate & Contract:

RESOLVED, that a resolution adopted by the City Council on December 23, 2024, and signed by the Mayor on December 24, 2024, authorizing the Mayor to Amend the Agreement with National Water Main Cleaning Company to Extend the Contract End Date for Outfall 24 Sewer System Cleaning and Inspection Project 122022-1 - (contract period to be extended from January 31, 2025, to March 31, 2025); be, and the same is hereby approved.
City Council:

AN ORDINANCE AUTHORIZING THE MAYOR TO
AMEND THE AGREEMENT WITH NATIONAL WATER
MAIN CLEANING COMPANY TO EXTEND THE
CONTRACT END DATE FOR OUTFALL 24 SEWER
SYSTEM CLEANING AND INSPECTION PROJECT 122022-1
Whereas, by letter dated December 17, 2024, the Commissioner of the Department of Public Works has requested legislation authorizing the Mayor to execute an amendment to the agreement with National Water Main Cleaning Company for the Outfall 24 Sewer System Cleaning and Inspection Project (Project No. 122022-1) to extend the contract end date from January 31, 2024, to March 31, 2025; and
Whereas, the City of Mount Vernon entered into an agreement with National Water Main Cleaning Company, located at 1806 Newark Turnpike, Kearny, New Jersey 07032, to clean and inspect all sewers within the area known as the Outfall 24 drainage area; and
Whereas, National Water Main Cleaning Company was selected as the low bidder for this project, and the contract was awarded for the amount of $1,661,800, which was approved on May 2, 2023; and
Whereas, the scope of work for the Outfall 24 drainage area includes the cleaning and inspection of all sewers within the area; and
Whereas, it has been determined that the Outfall 24 drainage area contains more sewers than initially anticipated, resulting in additional time needed to complete the work, which is currently 80% complete; and
Whereas, the existing contract with National Water Main Cleaning Company is set to expire on January 31, 2...