File #: TMP -982    Version: 1
Type: Ordinance Status: Adopted
File created: 10/17/2024 In control: City Council
On agenda: 11/19/2024 Final action: 11/13/2024
Title: Department of Public Works: An Ordinance to Authorizing the Mayor to Amend the Agreement with National Water Main Cleaning Company for the Cleaning and Inspection of Sewer Systems within Outfall 24 Drainage Area (Project 122022-1)
Attachments: 1. Contract Amendment Request -Outfall 24-Sewer System Cleaning and Inspection 122022-1.pdf

Board of Estimate & Contract:

 

RESOLVED, that a resolution adopted by the City Council on November 13, 2024, and signed by the Mayor on November 14, 2024, authorizing the Mayor to Amend the Agreement with National Water Main Cleaning Company for the Cleaning and Inspection of Sewer Systems within Outfall 24 Drainage Area (Project 122022-1) (funds required for this amendment shall be funded by the NYSDEC 2021 Water Quality Improvement Program Grant (WQIP) and any other applicable sources.  The funds shall be deposited into Revenue Code H3990 C937 and H3990 C938 (State Aid, Sewer Cap Pro) to be appropriated to Budget Code H8120.203 C937 and H8140.203 C938 (DPW sanitary and Storm Sewers) throughout the contract period); be, and the same is hereby approved.

City Council:

 

AN ORDINANCE AUTHORIZING THE MAYOR TO

AMEND THE AGREEMENT WITH NATIONAL

WATER MAIN CLEANING COMPANY FOR THE

CLEANING AND INSPECTION OF SEWER

SYSTEMS WITHIN OUTFALL 24 DRAINAGE AREA

 

Whereas, by letter dated October 23, 2024, the Commissioner of the Department of Public Works has requested legislation authorizing the Mayor to amend the agreement with National Water Main Cleaning Company for Project No. 122022-1, “Outfall 24 - Sewer System Cleaning and Inspection,” to increase the total contract amount by $700,000, for a new total of $2,361,800; and

Whereas, the City of Mount Vernon is committed to maintaining and improving its sewer system to ensure compliance with state and federal environmental regulations; and

Whereas, Project No. 122022-1, relating to the cleaning and inspection of sewers within the Outfall 24 drainage area, was awarded to National Water Main Cleaning Company on May 2, 2023, for $1,661,800, as the lowest responsive bidder; and

Whereas, the total sewer length in the Outfall 24 drainage area was initially estimated at 200,000 feet, but after further inspection, it was determined that the actual length is closer to 240,000 feet; and

Whereas, the amount of heavy cleaning required within this drainage area has also exceeded original estimates; and

Whereas, in order to complete the remaining sewer cleaning and inspection, an additional $700,000 is necessary, bringing the total project cost to $2,361,800; and

Whereas, this project is partially funded by the New York State Department of Environmental Conservation (NYSDEC) 2021 Water Quality Improvement Program Grant (WQIP); and

Whereas, the City is required to complete this work under the terms of a Consent Order, with a deadline for completion set for May 2025, making rebidding of the project impractical; Now, Therefore, Be It Resolved That

The City of Mount Vernon, in City Council convened, does hereby ordain and enact:

Section 1.                     Authorization to Amend Agreement.  The Mayor is hereby authorized to amend the agreement with National Water Main Cleaning Company for Project No. 122022-1, “Outfall 24 - Sewer System Cleaning and Inspection,” to increase the total contract amount by $700,000, for a new total of $2,361,800.

Section 2.                     Funding.  The additional funds required for this amendment shall be funded by the NYSDEC 2021 Water Quality Improvement Program Grant (WQIP) and any other applicable sources.  The funds shall be deposited into Revenue Code H3990 C937 and H3990 C938 (State Aid, Sewer Cap Pro) to be appropriated to Budget Code H8120.203 C937 and H8140.203 C938 (DPW sanitary and Storm Sewers) throughout the contract period.

Section 3.                     Scope of Work.  The project’s scope remains unchanged, and the additional costs are associated with the increased length of sewers and the extra heavy cleaning required within the Outfall 24 drainage area.

 

 

Section 4.                     Project Deadline.  The City shall ensure that all work is completed in accordance with the requirements of the Consent Order by the deadline of May 2025.

Section 5.                     Effective Date.  This ordinance shall take effect immediately upon its approval by the Board of Estimate & Contract.